Deepening and normalisation Pun Hlaing River

Location : Myanmar
Year : 2014

Deepening and normalisation of the Pun Hlaing River, Hlaing Thar Yar Township, in Myanmar.

Project was commissioned by the Irrigation department and will last till May 2015.

The total river length to be dredged is 30 miles.

The scope of installation are Hydraulic pump (HY85B) and cutter, control valve, piping kit, hoses, pipes and floaters.

The length of pipe for commissioning is 130m. The estimated production is 400cbm per hour.

The commissioning of the units was a huge success. Expected production and actual production is well within our calculation in the proposal. Contractor is very pleased with our work.